A Multi-Criteria Decision Framework for Optimal Rooftop Solar PV Site Selection in Industrial Zones: An AHP-Based Case Study in Central Java, Indonesia
DOI:
https://doi.org/10.55927/ijbae.v4i5.376Keywords:
Rooftop Solar PV, Site Selection, Analytical Hierarchy Process (AHP), Renewable Energy, Industrial SectorAbstract
Indonesia targets 23% renewable energy in its mix by 2025 and net-zero emissions by 2060, with rooftop solar PV (PLTS atap) offering strong potential for industrial applications. This study aims to identify the optimal site for rooftop solar installation across four industrial zones in Central Java (Brebes, Tegal, Jepara, and Rembang) using the Analytical Hierarchy Process (AHP). Data from expert stakeholders evaluated four main criteria—installed capacity, project cost, installation time, and quality—along with relevant sub-criteria. Results show installed capacity as the most influential criterion (weight 0.410), followed by cost (0.301), time (0.180), and quality (0.109), with dominant sub-criteria being roof area, EPC cost, installation duration, and safety-health-environment (SHE). The synthesis identifies Jepara as the optimal site (score 0.336), with all consistency ratios below 0.1 confirming result validity. This study provides a systematic decision-support framework for solar developers and policymakers while advancing SDG 7 and SDG 13.
References
Aditya, R., & Suryadi, H. (2021). Penerapan AHP dalam Penentuan Prioritas Lokasi PLTS Atap di Jawa Tengah. Jurnal Teknik Industri, 12(1), 45–52.
Al Garni, H. Z., & Awasthi, A. (2020). Solar site selection using AHP and PROMETHEE. Renewable and Sustainable Energy Reviews, 122, 109719.
Çoban, V. (2020). Solar energy plant project selection with AHP decision-making method based on hesitant fuzzy linguistic evaluation. Complex & Intelligent Systems, 6, 507–526.
Duran, O., Aguilar, C., & Jiménez, G. (2019). Multi-criteria decision analysis for solar power plant location selection in Ecuador. Renewable Energy, 143, 1471–1481.
Gunawan, & Hartono. (2020). Analisis Ekonomi PLTS Atap di Factory Garmen di Jawa Tengah. Jurnal Energi Terbarukan Indonesia, 9(1), 33–40.
Gupta, R., & Tiwari, G. N. (2021). Techno-economic evaluation of rooftop solar PV systems: A case study in India. Energy Conversion and Management, 231, 113782.
Heizer, J., Render, B., & Munson, C. (2017). Operations Management: Sustainability and Supply Chain Management (12th ed.). Pearson.
International Renewable Energy Agency (IRENA). (2022). Renewable Power Generation Costs in 2021. Abu Dhabi: IRENA.
Khoiroh, I. (2018). Manajemen Proyek: Perencanaan, Penjadwalan, dan Pengendalian. Yogyakarta: Penerbit Andi.
Kurniawan, R., Hasibuan, S., & Nugroho, R. E. (2017). Analisis Kriteria dan Proses Seleksi Kontraktor Chemical Sektor Hulu Migas: Aplikasi Metode Delphi-AHP. MIX: Jurnal Ilmiah Manajemen, 7(2), 252–266.
Ministry of Energy and Mineral Resources (ESDM), Indonesia. (2021). National Energy Policy.
Ministry of Energy and Mineral Resources (ESDM), Indonesia. (2023). Statistik Energi Terbarukan Indonesia.
Ministry of Industry, Indonesia. (2023). Electricity Consumption Report.
Nugroho, A., & Setiawan, B. (2023). Implementasi Permen ESDM No. 2 Tahun 2024 dalam Pemilihan Lokasi PLTS Atap. Jurnal Energi Terbarukan Indonesia, 10(1), 12–19.
Nugroho, R. E., & Pratama, M. I. (2023). Analysis of Delay in Secant Pile Foundation Work on the Semantok Dam Project. International Journal of New Technology and Research (IJNTR), 9(6), 24–34.
Oka, I. G. A., & Kartikasari, D. (2017). Manajemen Proyek: Perencanaan, Penjadwalan, dan Pengendalian. Penerbit Andi.
Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) (6th ed.).
Putra, A. S., & Prihantoko, B. (2021). Analisis Potensi Energi Surya di Wilayah Jawa Tengah Menggunakan Data Satelit. Jurnal Teknik Mesin UI, 20(1), 45–52.
Saaty, T. L. (2020). Decision Making for Leaders: The Analytic Hierarchy Process for Decisions in a Complex World. RWS Publications.
Saaty, T. L., & Ozdemir, M. S. (2003). Why the magic number seven plus or minus two. Mathematical and Computer Modelling, 38(3–4), 233–245.
Saputra, D., & Rahmawati, A. (2022). Evaluasi Teknis dan Finansial PLTS Atap di Perusahaan Manufaktur Rembang. Jurnal Teknik Elektro, 15(2), 112–120.
Silalahi, D. F., et al. (2021). Indonesia’s vast solar energy potential. Energies, 14(17), 5424.
Susilo, R., & Utomo, D. (2020). Studi Awal Pengembangan PLTS Atap di Kawasan Industri Tegal. Jurnal Energi Terbarukan, 8(2), 77–84.
United Nations. (2015). Transforming our world: the 2030 Agenda for Sustainable Development.
United Nations. (n.d.). Goal 7: Affordable and Clean Energy.
United Nations. (n.d.). Goal 13: Climate Action.
Wang, C.-N., et al. (2023). A decision-making model for solar energy plant project selection. Energies, 16(9), 4042.
Widyastuti, M., & Prasetyo, R. (2021). Optimasi Lokasi PLTS Atap Berbasis GIS dan AHP di Kota Semarang. Jurnal Rekayasa Sistem Industri, 7(2), 89–96.
Zhang, Y., Liu, H., & Wang, J. (2020). Integration of AHP and GIS for solar farm site selection. Energy, 200, 117522.
Downloads
Published
Issue
Section
License
Copyright (c) 2025 Ariyadi Widiatmoko, Rosalendro Eddy Nugroho

This work is licensed under a Creative Commons Attribution 4.0 International License.